CIAgent Grill Report
Run: 2026-09-27 11:25 (mode: mechanical, focus: all)
Verdict: Proceed (confidence: 0.72)
The plan is sound with fixable gaps. The evidence base is unusually strong for a project at P0: a shipped and owner-approved v0.1 (9 tags, decision commit 3fd0e10), a locked two-milestone structure, a typed frontend boundary already in the tree (client.ts), a research file with concrete API shapes, and honest ---ci--- reporting throughout. But the grill found two internal contradictions and one measurability hole that would each have surfaced at P3 as rework: (1) PLAN.md P1 claims REQ-07/REQ-12 delivery while ROADMAP/REQUIREMENTS/PLAN's own frontmatter map them to P2; (2) the approved prototype's ApiClient documents seven v0.2 endpoint mappings (GET /api/graph, GET /api/tasks, GET /api/library, GET /api/library/connections, GET /api/suggestions, POST /api/refine/*, PUT /api/config) that REQ-25 does not include — a hidden-scope grenade wired to the P3 swap; (3) REQ-23's ≥99% liveness bar cannot be proven in the zero-key test suite it is scheduled into. All three are absorbed below as binding decisions. The MVP does not overreach as specced — REQ-01..34 is a genuine core loop — but the implicit live-mode expectation (whole prototype UI working against the backend) does overreach, and is explicitly reduced to the core research loop (G-002, escalated for owner ratification at the P5 gate).
Axis 1 — Business Case
- Q1: What problem does this actually solve, and is that problem still the top priority?
- Evidence: PROJECT.md Core Value + Key Decisions ("deep-research agents hallucinate URLs at the highest measured rates; verification cuts failures to <1% [E1]"); owner approved v0.1.8 and immediately unblocked v0.2 (commits
3fd0e10,42435bc). - Answer: Real, named problem — citation-untrustworthy deep-research agents — converted into a differentiated product thesis (methodology-first + trust loop). The owner's same-day unblocking of v0.2 shows it remains the top priority. Not a project that outlived its justification: the value is entirely unrealized until the MVP ships, which argues for proceeding, not stopping.
- Confidence: 0.80
- Evidence: PROJECT.md Core Value + Key Decisions ("deep-research agents hallucinate URLs at the highest measured rates; verification cuts failures to <1% [E1]"); owner approved v0.1.8 and immediately unblocked v0.2 (commits
- Q2: Who is the named executive sponsor, and when did they last make a decision under pressure?
- Evidence: Owner decisions under pressure recorded twice in v0.1: P4 gate returned feedback instead of approval → binding P5/P6 extension (ROADMAP P4 note, commit
7db53d62); P6 gate returned 2nd feedback → P7/P8 extension (commit57c5231, ROADMAP P6 note); final approval3fd0e10. D-018/D-019 record owner directives for this run. - Answer: The sponsor is pressure-tested, not a rubber stamp — two rejections/extensions before approval. This is the strongest possible sponsor signal available in the record.
- Confidence: 0.85
- Evidence: Owner decisions under pressure recorded twice in v0.1: P4 gate returned feedback instead of approval → binding P5/P6 extension (ROADMAP P4 note, commit
- Q3: What happens to the business if the project is cancelled?
- Evidence: v0.1 is mock-only by design (REQ-53: "no backend, no API keys"); zero research value has shipped; all value lands in v0.2 (REQ-01..34).
- Answer: Cancelling now strands 100% of sunk effort — the prototype is a shell without the MVP. The project is not a zombie; it is the opposite: a project whose entire value is still ahead of it, which raises the stakes of P2/P3 execution quality, not the case for stopping.
- Confidence: 0.75
- Q4: Is the ROI calculated against a counterfactual?
- Evidence: MISSING — no ROI/counterfactual calculation exists anywhere in .ciagent/.
- Answer: No formal ROI. The implicit counterfactual is "ad-hoc LLM prompting with unverified citations," which is plausible but never quantified. For an owner-directed, single-user, local-first tool this is a tolerable omission — the sponsor is the beneficiary — but it means priority calls rest entirely on owner judgment, with no objective measure if enthusiasm fades.
- Confidence: 0.55
- Decision: G-007 — make the counterfactual measurable in-product: per-run request/token/cost counters in the run trace, surfaced via
GET /api/config(advisory, no hard spend cap in MVP). This is the cheapest honest ROI instrumentation available.
Axis 2 — Scope and Requirements
- Q1: Is the scope expanding, contracting, or genuinely stable?
- Evidence: REQ-01..34 locked with traceability (REQUIREMENTS.md table); D-007..D-020 clarify commit recorded (
e79102b); v0.1 scope grew twice via owner gate feedback (P5/P7 extensions) — proof the gate can grow scope. - Answer: The formal scope is stable and frozen. But the grill found the informal scope is ambiguous: the prototype's approved UI implies backend endpoints that REQ-25 does not promise (see Q4). That ambiguity will resolve itself at P3 — either as scope growth or as a visible degraded mode. It must be resolved now, in writing.
- Confidence: 0.60
- Evidence: REQ-01..34 locked with traceability (REQUIREMENTS.md table); D-007..D-020 clarify commit recorded (
- Q2: Who owns the requirements, and have they been frozen?
- Evidence: Owner-approved milestone structure (PROJECT.md Constraints); REQUIREMENTS.md traceability with per-phase status; clarify decisions D-007..D-020 at confidence 0.75–1.0.
- Answer: Owner owns; the pipeline freezes and traces them. Requirements management is this project's strongest discipline.
- Confidence: 0.85
- Q3: What is explicitly out of scope?
- Evidence: REQUIREMENTS.md "Out of Scope" table (paywalled sources, chatbot/hosting, auth/multi-tenancy, native Ollama adapter, rename, autonomous v1.0.0); PROJECT.md Out of Scope.
- Answer: Explicit, reasoned, and enforced (e.g., OpenAI-compatible-only is restated in constraints and architecture).
- Confidence: 0.90
- Q4: Are there hidden requirements only disclosed late in delivery?
- Evidence: FOUND — two. (a)
frontend/src/lib/api/client.tslines 123–179 document v0.2 mappings toGET /api/graph,GET /api/tasks,GET /api/library,GET /api/library/connections,GET /api/suggestions,POST /api/refine/questions,POST /api/refine/compose,PUT /api/config— none of which appear in REQ-25 (runs, methodologies, lifecycle, SSE, config-read only) or any v0.2 phase mapping. (b) The same file exposes nopauseRun/resumeRunwhile REQ-25 mandates pause/resume in the API and REQ-15 mandates server-side pause/resume across restarts; line 69's comment claims "pause/resume stay client-side concerns," which contradicts the engine requirement. - Answer: The P3 swap ("behind the unchanged ApiClient interface," REQ-26/REQ-54) is wired to detonate: either the backend grows 7+ undocumented endpoints (scope expansion inside the MVP milestone), or live mode silently breaks six approved UI surfaces, or the interface changes anyway (breaking REQ-54's zero-rewrite promise without a plan). This is the single largest finding of this grill.
- Confidence: 0.50
- Decision: G-002 — declare the v0.2 live-mode surface = core research loop only (Ask, Choose, Plan & Run, Reading Room + read-only
GET /api/config); Library, Settings persistence, Suggestions, Refine, project graph, task inbox, and user profile stay mock-bound behind ApiClient in live mode, honestly marked in-UI, with their backends explicitly deferred to v0.3+. G-003 — addpauseRun/resumeRunto ApiClient in P3 as the single planned, documented interface extension (mock gains matching implementations), superseding the v0.1 client-side-pause comment; REQ-54's zero-rewrite promise is amended to "no unplanned rewrites." - Escalation: [G-009] — owner must ratify the live-mode boundary at the P5 gate (see Escalations).
- Evidence: FOUND — two. (a)
Axis 3 — Architecture and Technical Feasibility
- Q1: Has the architecture been validated by the people who will build and operate it?
- Evidence: RESEARCH-v02.md — 8 topics with concrete API payload shapes, pitfalls, and 14 conclusions written for the builders (pydantic event unions, shielded state writes,
os.replaceatomicity, pytest-asyncio modes, hatchlingpackageskey). Butbackend/does not exist yet — zero lines of the architecture have run. - Answer: Design-side validation is strong (this is what a builder-facing research doc should look like); runtime validation is zero, by definition of P0. The risk concentrates at first contact: ollama.com/v1 shapes, Tavily payload, SSE backpressure. P1 Wave 3 is the first live proof.
- Confidence: 0.65
- Evidence: RESEARCH-v02.md — 8 topics with concrete API payload shapes, pitfalls, and 14 conclusions written for the builders (pydantic event unions, shielded state writes,
- Q2: What is the integration surface, and where does it quietly double in cost?
- Evidence: Five adapter slots (ARCHITECTURE §2); SSE transport (D-014); OpenAPI client generation (D-013, RESEARCH §7 — flags operation-id stability and regen-from-snapshot discipline as pitfalls); the ApiClient surface gap (Axis 2 Q4).
- Answer: 5 adapters + SSE + codegen swap = 7 integration seams. The cost-doubling candidate is the P3 swap (seam #7) — precisely where the undocumented-endpoint problem sits. Second candidate: the openapi.json snapshot discipline exists only as a research pitfall note, not a P3 must-have.
- Confidence: 0.60
- Decision: G-005 — P3 must-have: commit the backend
openapi.jsonsnapshot; regeneratefrontend/src/lib/api/generated/only from the snapshot (never a live server); add a schema-drift check to the gates; fix FastAPI operation-ids at route creation.
- Q3: Is there an existing system being replaced — actual data volume, transaction rate, edge-case behavior?
- Evidence: Greenfield backend; the "replaced system" is
MockApiClient(fixtures + scripted replay, frontend/src/lib/api/mock/). REQ-54 defines the swap contract; PERSONAS.md binds the frontend-engineer to it. - Answer: No data migration risk. The migration is one interface binding line (client.ts:187) — provided G-002/G-003 are absorbed; otherwise the "small migration" is the biggest one in the project.
- Confidence: 0.70
- Evidence: Greenfield backend; the "replaced system" is
- Q4: What technical debt is inherited, and is it budgeted for?
- Evidence: (a) the v0.1 "client-side pause" comment (client.ts:69) contradicting REQ-15 — budgeted via G-003. (b) DDG
html.duckduckgo.com/htmlscrape as the keyless fallback (D-012, confidence 0.75) — RESEARCH §3 itself warns "rate-limits aggressively... best-effort." (c) Scripted-replay SSE shape must match D-014's event union — verified aligned (D-014 rationale cites the MockApiClient replay contract). - Answer: The DDG fallback is the fragility hotspot: a legacy HTML surface, conservatively scraped, that the research file already expects to fail. The zero-config promise of the product rests partly on it. Mitigation exists in design (surfaced warning, never hang) but is not yet test-enforced.
- Confidence: 0.55
- Decision: G-008 — DDG fallback is tested against recorded HTML fixtures only (never live-scraped in CI); the degradation contract (partial/empty results + typed warning, never hang, never block the engine) is asserted by test. DDG is documented as degraded-mode, not a reliable second source.
- Evidence: (a) the v0.1 "client-side pause" comment (client.ts:69) contradicting REQ-15 — budgeted via G-003. (b) DDG
Axis 4 — People, Skills, and Organization
- Q1: Which 2–3 people, if they left, would the project fail?
- Evidence: The entire delivery capability is one agent pipeline (coreci) + one owner (decision commit 3fd0e10; all directives owner-recorded). PERSONAS.md is a persona roster, not a human team.
- Answer: Key-person dependency is total and structural: owner disengagement stalls every gate by design (that is the governance model); pipeline failure stops all delivery. For a single-user, owner-directed tool this is acceptable — but it means timeline estimates are really "pipeline availability" estimates, and there is no bench.
- Confidence: 0.60
- Q2: Are resources actually allocated at the percentages claimed?
- Evidence: Autonomy level "full" (config.json); v0.1 shipped 9 phases, PRs #1–#8, tags v0.1.0–v0.1.8 within ~10 hours of wall clock (commits
dd2538f00:44 →d6ddcfe10:03, 2026-09-27). - Answer: The pipeline is demonstrably 100% allocated and not fighting BAU fires — velocity is exceptional and verified by artifact trail, not status reports.
- Confidence: 0.85
- Evidence: Autonomy level "full" (config.json); v0.1 shipped 9 phases, PRs #1–#8, tags v0.1.0–v0.1.8 within ~10 hours of wall clock (commits
- Q3: Is there a product owner with actual authority to prioritize?
- Evidence: Owner directives recorded as binding decisions (D-018, D-019 at confidence 1.0); two gate rejections prove authority in practice.
- Answer: Unambiguous single owner; no committee. Model is working.
- Confidence: 0.90
- Q4: Is the team building capability it doesn't have, hoping to learn as they go?
- Evidence: The stack is being built in-milestone: FastAPI, asyncio durability (shielded writes, CancelledError discipline — RESEARCH §5), sse-starlette, httpx adapters, openapi codegen. No backend code exists yet (repo is frontend-only today). RESEARCH-v02.md documents the failure modes in advance (pytest-asyncio event_loop removal, hatchling src-layout wheel pitfall, uvicorn single-worker constraint).
- Answer: Yes, capability is being built on the fly — acceptable here because (a) this is a prototype-to-MVP transition with research-backed patterns, and (b) zero-key fakes (REQ-31) mean the engine can be proven without live services. But P2 is where "learning asyncio under load" meets "13 requirements" — see Axis 5.
- Confidence: 0.60
Axis 5 — Timeline and Estimates
- Q1: Was the deadline set before or after scope and approach were understood?
- Evidence: No wall-clock deadlines exist anywhere in ROADMAP v0.2 — sequencing is dependency-driven (P0→P5), cadence is owner gates (D-018: halt at the owner approval gate).
- Answer: No reverse-engineered deadline — the healthiest possible pattern. The only "date" is the owner's attention, which v0.1 proved is present.
- Confidence: 0.85
- Q2: What is the critical path, and what single thing would push it by 3+ months?
- Evidence: Critical path P1 → P2 → P3 → P4 (sequential phases, ROADMAP). P2 is the milestone's heaviest phase: 13 requirements (REQ-07, 12, 13–24) including the durable asyncio state machine, trust loop, and live probing. The 3-month pusher is a P3 integration-drift discovery: the ApiClient surface gap (Axis 2 Q4) hitting mid-swap, after P2's engine is built against the wrong boundary assumptions.
- Answer: Critical path is P2-heavy and P3-fragile. G-002/G-003 defuse the P3 risk; P2's size needs a pressure valve.
- Confidence: 0.70
- Decision: G-006 — permit P2 to ship as two patches (P2a: engine + durable state + SSE; P2b: trust loop + live probe/REQ-07/12) or run mid-phase wave gates, without changing milestone scope; the P3 swap plan (endpoint list per G-002) must be drafted at P2 start, not P3 start, so drift surfaces before the engine is frozen.
- Q3: Are the estimates evidence-based?
- Evidence: The only velocity base is v0.1: ~1 phase/hour sustained across 9 phases including review+audit each. v0.2 phases are materially heavier (greenfield backend, adversarial tests). MISSING: any per-phase sizing in ROADMAP/PLAN.
- Answer: No estimates exist to be wrong — but also none to be right. v0.1 velocity does not transfer 1:1 (frontend screens vs. a durable async engine); treating it as a base rate would understate P2. The mitigation is the phase-patch mechanism (G-006) rather than fake numbers, which this grill endorses over invented estimates.
- Confidence: 0.60
- Q4: Is there a working definition of done?
- Evidence: Per-phase success criteria (ROADMAP); PLAN.md gates + "REQ coverage assert: each REQ mapped to ≥1 test or contract proof"; verify stage precedent (PASS-WITH-FIXES with in-phase P0 fixes, PRs #4/#6/#8); final owner gate.
- Answer: Yes, and it is enforced — v0.1 reviews fixed 5 P0s and multiple P1s in-phase, which is proof the DoD has teeth.
- Confidence: 0.85
- Decision: G-001 — resolve a DoD contradiction inside P1's own plan: PLAN.md must_haves and tasks T-1.10/T-1.11 claim REQ-07/REQ-12 delivery ("GET /models + structured-output smoke test" = live probing) while PLAN's frontmatter (
requirements: [REQ-01..06, 08..11, 31]), ROADMAP P1 ("REQ-07, REQ-12 ship in P2... live probing against real endpoints in P2"), and REQUIREMENTS traceability all map them to P2. Binding: P1 ships the typed ProbeResult + structured-output warning contracts proven with fake adapters; live endpoint probing executes in P2 with the engine. Secondary bookkeeping fix in the same decision: the "REQ-13..24" range notation includes REQ-17 in both P2 and P4 rows — REQ-17 (3-click on real stack) stays in P4; ranges are corrected to exclude it.
Axis 6 — Budget and Financial Realism
- Q1: What percentage of budget is spent vs. remaining?
- Evidence: MISSING — no cost ledger exists. Known spends: pipeline tokens (v0.1: 9 phases of agent execution; v0.2 P0 stages), Ollama cloud key (config.json secrets scope
model), Tavily key (scopesearch), self-hosted LXC infra (DEPLOY-RECORD.md). - Answer: Untracked. For a single-user local-first tool the absolute numbers are small, but "untracked" is still a finding: no one can currently answer what a Deep Report run costs.
- Confidence: 0.60
- Evidence: MISSING — no cost ledger exists. Known spends: pipeline tokens (v0.1: 9 phases of agent execution; v0.2 P0 stages), Ollama cloud key (config.json secrets scope
- Q2: Are there predictable cost drivers not in the original budget?
- Evidence: Deep Report = depth 3/breadth 2 → per run: ~dozens of model calls (planner + depth-loop reflections + writer + verification passes) plus search calls; Ollama cloud is pay-per-use; Tavily free tier is quota-capped; DDG fallback is free-but-fragile (D-012). Localhost:11434 fallback is the zero-cost escape hatch (REQ-08).
- Answer: Cost drivers are real and unbounded per run (no request caps on loops beyond dial defaults). The local-fallback design keeps the project from hard dependency on spend, but there is no visibility.
- Confidence: 0.60
- Decision: G-007 — per-run counters (model requests, tokens, search calls) recorded in the run trace and surfaced via
GET /api/config; advisory only in MVP.
- Q3: Burn rate and runway?
- Evidence: MISSING formal tracking; mitigated by local-first defaults (keyless localhost fallback, DDG keyless fallback) meaning the runway floor is "zero marginal cost, degraded mode."
- Answer: The architecture is honest about this: the product's default posture degrades to free. Runway is effectively unbounded if the owner accepts degraded mode; the grill accepts this as sound for the MVP.
- Confidence: 0.70
- Q4: Is the budget contingent on something that hasn't happened yet?
- Evidence: No — no sale/board/hiring dependency. Keys exist (config.json scopes), infra exists (LXC), pipeline is running.
- Answer: Not contingent. Proceed.
- Confidence: 0.80
Axis 7 — Risks, Assumptions, and Dependencies
- Q1: Top 3 assumptions, and evidence for each?
- Evidence: (a) Adapter endpoint compatibility — ollama.com/v1 OpenAI-shape and Tavily POST payload researched with concrete shapes (RESEARCH §2/§3), but unvalidated live in-repo; P1 Wave 3 is the test. (b) DDG fallback stability — RESEARCH §3 itself rates it "best-effort, aggressively rate-limited" (weakest assumption in the plan; D-012 confidence 0.75). (c) Zero-rewrite client swap — typed boundary exists (client.ts), RESEARCHX_API_MODE designed (D-020), but the interface gaps (Axis 2 Q4) undercut it until G-002/G-003 land.
- Answer: Two of three are well-evidenced; the DDG assumption is the one the project's own research argues against relying on. All three have named first-contact phases (P1 Wave 3, P2, P3).
- Confidence: 0.60
- Decision: G-008 (fixture-tested DDG degradation contract) — see Axis 3 Q4.
- Q2: External dependencies outside the team?
- Evidence: Tavily quota; Ollama cloud key validity; DDG uncontrolled HTML surface; none of these are under the project's control; all have fallbacks except Tavily→DDG quality.
- Answer: Dependencies are acknowledged with degradation paths — the correct posture. The unmitigated residual is degraded search quality when Tavily is exhausted, which directly attacks the ≥99% liveness bar.
- Confidence: 0.65
- Q3: The single risk that kills the project, and is there a mitigation?
- Evidence: P3 swap discovering the ApiClient/surface drift after the engine is frozen (evidence chain: client.ts:123–179 vs REQ-25; ROADMAP P3 "the ApiClient interface absorbs any prototype-era API drift" — an assertion, not a plan).
- Answer: Kill risk = integration drift at P3 → rework spiral through a hand-rolled engine → owner patience (already tested twice by extensions) exhausts. Mitigation now exists in writing: G-002 (boundary declared), G-003 (interface change planned), G-005 (snapshot discipline), G-006 (P3 plan drafted at P2 start). This grill's core job is done if those four hold.
- Confidence: 0.65
- Q4: Has a pre-mortem been done?
- Evidence: MISSING — no pre-mortem artifact. This grill is the closest proxy.
- Answer: "It's 12 months out and v0.2 failed" — the derivable causes, in order: (1) P3 surface gap hit late (mitigated: G-002/003/005/006); (2) P2 asyncio durability bugs (pause/resume across restarts is genuinely hard — mitigated by RESEARCH §5 patterns + REQ-32 pause-mid-depth-loop adversarial tests); (3) quote anchoring thrash on real noisy pages (difflib 0.85 is fixture-proven only — live-page behavior unknown until P4/live runs); (4) DDG dead + Tavily exhausted → un-demoable zero-config mode (mitigated: G-008 + owner-held Tavily key).
- Confidence: 0.60
Axis 8 — Governance, Decision-Making, and Communication
- Q1: Who is the decision-maker when two parties disagree?
- Evidence: Single owner; all decisions recorded as decision commits (3fd0e10; D-007..D-020 in
e79102b); escalation hooks codified in config.json (deploy, delete_data, merge_to_main, prototype_approval). - Answer: Unambiguous. No dual-executive stall is possible in this structure.
- Confidence: 0.90
- Evidence: Single owner; all decisions recorded as decision commits (3fd0e10; D-007..D-020 in
- Q2: Governance cadence and escalation pattern — useful in a crisis?
- Evidence: Per-phase ship + verify + audit with
---ci---blocks; v0.1 precedent: pipeline halted itself at gates twice (7db53d62,57c5231) rather than self-approving — the escalation pattern is proven under the exact stress it exists for. - Answer: Cadence is per-phase and gates have been exercised under pressure. Crisis-tested by construction.
- Confidence: 0.85
- Evidence: Per-phase ship + verify + audit with
- Q3: What is being omitted from status reports?
- Evidence: Honest reporting verified in history: "PASS-WITH-FIXES," "PASS-WITH-NOTES," "approval_pending," P0s disclosed and fixed in-phase; DEPLOY-RECORD.md as a separate ledger. The one systemic omission this grill found lives in spec comments, not status blocks: the client.ts v0.2 endpoint mappings that were never promoted into REQUIREMENTS — a silent scope assumption, now surfaced (G-002).
- Answer: Status reporting is honest. Spec-side implication drift is the channel where optimism leaked — and it's now on the record.
- Confidence: 0.80
- Q4: Is there a stop-the-project trigger?
- Evidence: Owner rejection at gate → binding fix cycle (v0.1 exercised twice); v1.0.0 owner-only (config.json major_locked); D-018 halts at the v0.2 gate; D-019 forbids deploys without directive.
- Answer: Yes — and rejection has demonstrably not become politically impossible; the owner said "not yet, extend" twice without ceremony.
- Confidence: 0.85
Axis 9 — Change, Adoption, and Operational Readiness
- Q1: Who will use this, how does their work change, and what's in it for them?
- Evidence: Single-user owner-researcher (PROJECT.md constraint: "Single-user, local-first"); work change = ad-hoc prompting → structured, reproducible methodology runs with auditable citations (REQ-04 dial snapshots, REQ-21 ledger, REQ-22 checklist).
- Answer: The user is the sponsor — adoption politics are minimal, and the value proposition (trustable citations) is the same thesis the sponsor approved twice. The real adoption test is whether live-mode runs feel better than the mock — which lands at P4/REQ-17.
- Confidence: 0.80
- Q2: Is ops involved now, or handed a finished product at go-live?
- Evidence: The pipeline is ops: deploy.sh with rolling swap +
researchx-prevrollback container (commit2ffc71c), gates re-run at deploy time (DEPLOY-RECORD.md rows), VERSIONING.md rules. Gap: the deploy system is frontend-only; the MVP's live mode requires a local backend process (uvicorn, single worker — RESEARCH §4) whose serving story at the owner gate is undefined (D-019 forbids deploys without directive, so live-mode presentation mode is an open question). - Answer: Ops is built-in and rollback-capable for the frontend. The backend has no deploy story — coherent with local-first, but it means the P5 owner-gate demo of the live MVP needs a plan (local backend + keys at demo time, or gate runs on mock mode). This rides with G-009.
- Confidence: 0.60
- Evidence: The pipeline is ops: deploy.sh with rolling swap +
- Q3: What is the rollback plan?
- Evidence: Tags v0.1.0–v0.1.8 preserve history; deploy.sh swaps containers with a
researchx-prevrollback; durable run state is per-run JSON on local disk (D-017) — engine changes cannot corrupt other runs' state; frontend mock mode (RESEARCHX_API_MODE=mock default, D-020) is itself a rollback for the entire live integration. - Answer: Multi-layer rollback exists and is codified. The mock-default flag is an unusually good one — the MVP can ship with live mode opt-in, making go-live risk nearly zero.
- Confidence: 0.80
- Evidence: Tags v0.1.0–v0.1.8 preserve history; deploy.sh swaps containers with a
- Q4: Have success criteria been validated with the people who will judge success?
- Evidence: REQ-17 (≤3 clicks on real stack) is P4-tested, validated on mock in v0.1 (REQ-61 pinned by test). REQ-23 (≥99% citation liveness) — measurement gap: the entire adversarial suite is zero-key on a 5–8 page fixture corpus (RESEARCH §5b); 99% liveness on fixture URLs is vacuous, and no keyed/live validation run is scheduled anywhere in P1–P5.
- Answer: The 99% bar — the project's headline promise — is currently scheduled to be "verified" in a harness that cannot verify it. If the owner gate treats REQ-23 as CI-green, the status report will be honest-looking but hollow.
- Confidence: 0.55
- Decision: G-004 — REQ-23 is defined as a runtime per-run gate enforced at export (failures listed in the verification checklist, REQ-22) plus an opt-in, keyed, live-URL test tier (skipped by default, run before ships at owner discretion); P4 proves the gate mechanics with fixtures and explicitly does not claim live 99% attainment. The MVP definition of done for REQ-23 = the gate exists and enforces, not "CI showed 99%."
Meta — Closing Review
- Q1: If you were the auditor, what would you flag?
- Evidence: The two internal contradictions (PLAN vs ROADMAP/REQUIREMENTS on REQ-07/12, PLAN must_haves vs PLAN frontmatter; REQ-17 double-mapped in range notation) and the spec-comment endpoint mappings outside REQ-25 (client.ts:123–179).
- Answer: Flag #1: phase-mapping integrity — the traceability table is the single source of truth and PLAN must conform to it (G-001). Flag #2: an approved artifact (client.ts) documents v0.2 API surface that the v0.2 spec does not contain — the grill treats this as the most consequential process lapse found, because it would have surfaced as a P3 "surprise" after the engine was frozen.
- Confidence: 0.75
- Q2: What is the project not doing that it should?
- Evidence: Missing items found across axes: openapi snapshot drift check as a gate (G-005), per-run cost counters (G-007), live-URL test tier for REQ-23 (G-004), P3 swap plan at P2 start (G-006), fixture-based DDG tests (G-008), live-mode boundary declaration (G-002).
- Answer: All six are now bound. Nothing found suggests the project is doing something it should not.
- Confidence: 0.75
- Q3: What is the simplest version that delivers 80% of the value?
- Evidence: The MVP already trimmed to 2 of 8 methodologies (REQ-03) and a core-loop-only API (REQ-25). The remaining 20% of complexity carrying outsized risk: Deep Report's depth-3 breadth-2 loop (multiplies engine, trust, and cost surface) vs. Rapid Answer's depth-1 single-pass core.
- Answer: Rapid Answer alone + trust loop = 80% of the thesis proof. Deep Report is the pre-agreed deferral lever if P2 overruns — decided now, while it is cheap, rather than mid-crisis.
- Confidence: 0.65
- Decision: G-010 — contingency lever, pre-agreed: if P2/P4 slip beyond one extension cycle, Deep Report (REQ-03 partial) defers to v0.3 and the MVP ships Rapid Answer end-to-end; the lever requires owner sign-off when pulled, per gate rules.
- Q4: What must be true for this to succeed in the next 90 days, and is it true today?
- Evidence: Required: (a) researched adapter shapes hold live (untested — first proof P1 Wave 3); (b) owner engagement continues (proven: 3 gate decisions in one day); (c) Tavily key active/quota available (held in secrets scope; unverified live); (d) the P3 boundary is as declared in G-002 (currently not true in writing — client.ts says otherwise).
- Answer: Three of four are true or evidenced; (d) becomes true when the orchestrator promotes G-002/G-003. That promotion is the gating action of this entire grill.
- Confidence: 0.70
Binding Decisions
| ID | Axis | Decision | Confidence |
|---|---|---|---|
| G-001 | 2/5 | Resolve the REQ-07/REQ-12 phase contradiction in PLAN.md's favor of the ROADMAP/traceability mapping: P1 ships typed probe/warning contracts proven with fakes; live endpoint probing (GET /models, structured-output smoke test) executes in P2. Reword PLAN must_haves T-1.10/T-1.11 to contract level; fix the REQ-13..24 range notation so REQ-17 appears only in P4. | 0.85 |
| G-002 | 2/3 | Declare v0.2 live-mode surface = core research loop only (Ask, Choose, Plan & Run, Reading Room, read-only GET /api/config). Library, Settings persistence, Suggestions, Refine, project graph, task inbox, user profile stay mock-bound in live mode, honestly marked; their backends are v0.3+ scope. Update client.ts v0.2-mapping comments accordingly. | 0.80 |
| G-003 | 3 | Add pauseRun/resumeRun to the ApiClient interface in P3 as the single planned, documented interface extension (mock gains matching implementations); run-level pause is server-side per REQ-15/REQ-25, superseding the v0.1 "client-side concerns" comment. REQ-54 amended: no unplanned rewrites. |
0.80 |
| G-004 | 7/9 | REQ-23 (≥99% liveness) is a runtime per-run gate enforced at export and surfaced in the verification checklist — not a zero-key CI assertion. Add an opt-in keyed live-URL test tier (skipped by default). P4 proves gate mechanics with fixtures; MVP DoD for REQ-23 = the gate exists and enforces. | 0.75 |
| G-005 | 3/5 | P3 must-have: commit the backend openapi.json snapshot; regenerate frontend/src/lib/api/generated/ only from the snapshot; add a schema-drift check to gates; fix FastAPI operation-ids at route creation. | 0.85 |
| G-006 | 5 | Permit P2 (13 REQs — heaviest phase) to ship as two patches (P2a engine+durable state+SSE, P2b trust loop+live probe) or run mid-phase wave gates without milestone scope change; draft the P3 swap endpoint plan (per G-002) at P2 start, not P3 start. | 0.70 |
| G-007 | 1/6 | Per-run advisory counters (model requests, tokens, search calls) recorded in the run trace and surfaced via GET /api/config — the cheapest honest ROI/burn instrumentation; no hard spend cap in MVP. | 0.70 |
| G-008 | 3/7 | DDG fallback tested against recorded HTML fixtures only (never live-scraped in CI); degradation contract (partial/empty + typed warning, never hang the engine) asserted by test; DDG documented as degraded-mode, not a reliable second source. | 0.70 |
| G-010 | Meta | Pre-agreed contingency lever: if P2/P4 slip beyond one extension cycle, Deep Report (depth 3) defers to v0.3 and the MVP ships Rapid Answer end-to-end; pulling the lever requires owner sign-off at a gate. | 0.65 |
Escalations
- [G-009] Axis 2 — Owner ratification required at the P5 gate (D-018 halt): the v0.2 MVP demonstrates the live core research loop only; the remaining approved-prototype surfaces (Library, Settings persistence, Suggestions, Refine, graph/inbox previews, profile) remain mock-bound until v0.3+, and the live-mode gate demo requires a local backend + keys (or runs in mock mode) since D-019 forbids deploys. This redefines what "MVP done" looks like at the demo and must not be discovered by the owner at the gate — it must be ratified in advance. Engineering-side handling is bound in G-002/G-003; the ratification itself is unresolved until the owner records it.
- RESOLVED 2026-09-27: RATIFIED. Owner approval recorded via /ci-run 'APPROVED' at the v0.2.5 gate (decision commit
4721c2a), following the owner-directed UAT staging at https://research.coreci.dev. Live-mode scope = core research loop only is the accepted MVP boundary; mock-bound surfaces move to v0.3+.
- RESOLVED 2026-09-27: RATIFIED. Owner approval recorded via /ci-run 'APPROVED' at the v0.2.5 gate (decision commit